FEATURE PROJECT:
SATALA POWER PLANT REPLACEMENT
SERVICES:
QC Management
​
In 2009 a tsunami damaged the local power plant in Pago Pago, American Samoa, and a new 23MW power plant was to be constructed. Louis Berger Power contracted Amorient to provide Construction Quality Control Management for this project.
​
The scope of work involved all QC/QA programs for the construction and equipment installation, which included earthwork, concrete construction, pre-engineered building erection, mechanical (incl. HVAC), electrical and fire suppression systems.